Common refusals of extensions of time
Construction contracts generally allow the construction period to be extended where there is a delay that is not the contractor's fault. This is described as an extension of time (EOT).
When it becomes reasonably apparent that there is, or that there is likely to be, a delay that could merit an extension of time, the contractor should give written notice to the contract administrator identifying the relevant event that has caused the delay. If the contract administrator accepts that the delay was caused by a relevant event, then they may grant an extension of time and the completion date is adjusted.
Common reasons for the refusal of an application for extensions of time include:
- Where the contractor has underperformed, for example, as a result of insufficient workforce or failure to obtain plant, goods or service.
- When there has been poor, but not exceptionally adverse weather.
- When the evidence or other information presented to demonstrate that the contractor has suffered irrecoverable delays is insufficient.
- If an extension of time has already been given for that event.
- Where more than one event occurs at the same time. See Concurrent delay for more information.
- The event cited does not constitute a relevant event.
- An event does not constitute force majeure.
- An event does not constitute a specified peril.
- The contractor has not taken steps to mitigate the delay
[edit] Related articles on Designing Buildings Wiki
- Acceleration of construction works.
- Change order.
- Compensation event.
- Contract administrator.
- Contract claims.
- Culpable delay.
- Delay damages.
- Extension of time.
- Extension of time - approval letter example.
- How to prepare a claim for an extension of time.
- Practical completion.
- Project programme.
- Time certainty.
- Time extension.
- Time Risk Allowance TRA.
- Variations.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
ECA calls for an exemption for contractors working away from home.
Fire performance of thermal insulation
Flat roof assemblies with PV.
Become a Professional Development Partner
CIOB launches a new framework for staff development and chartered membership.
Dorset's first conservation campaigner?
Gov.uk - Hot-rolled steel plate
New anti-dumping measure imposed on South Korea.
ECA responds to the Milburn Report
Youth employment to be linked to workforce demand.
The construction industry urgently needs to attract new talent
CIOB responds to Neets report.
Grenfell Tower community update
Memorial columns to be retained as careful dismantling continues.
When buildings reflected the local resources available.
CIOB reports 57% are using artificial intelligence technologies.
More of England’s ‘hidden heroes’ will be celebrated.
CIAT calls for retrofit to be a priority.
















